Texas / Federal
Summit Texas Clean Energy carbon capture
This Texas carbon-capture project received about $117.88 million in federal funding, but the facility was not built. Funding for the early stage far exceeded the original plan.
Audit findings; facility not built
Ask Impact Analyst
Ask about the numbers or evidence. Keep the conversation going with follow-up questions.
By sending, you agree to share your question and this case’s notes with Google Gemini and save the conversation privately for review. Privacy
What was the money for?
Develop a coal-based power project with carbon capture in Texas.
The $117.88 million is actual Energy Department project funding reported in a 2021 federal audit. It does not measure the value of work that remained usable.
Exact amount, time period and source wording
Actual DOE project funding reported by GAO
Period: GAO 2021 review
Putting the amount in context
the funding planned for the stage reached
Reported funding of $117.88 million was about 7.86 times the roughly $15 million planned for that stage.
What this comparison means: That is about 686% above the plan, not 786% above it. It is not the full plant cost or a measured fraud loss.
How we calculated this and where it comes from
117,876,707 / 15,001,312
786% of plan means 686% over plan. Not full plant cost or measured fraud.
What actually happened?
The funding agreement ended without the facility being built.
Keep in mind: Exceeding the funding plan does not prove design costs were stolen. The amount is already part of the audit’s broader project total.
Read the detailed findings
GAO reports actual early-phase funding at roughly 786% of the $15 million initially planned for the phase reached.
Reported status: Funding agreement terminated; facility was not built.
The management failure does not establish that design costs were stolen. This project is already included in the broader four-project total.
Can we follow the payments?
A report can tell us the total. To follow the money, we also need to connect each bill to a payment and to what was received.
Payment records and reporting periods · reviewed November 9, 2026
What could a 3-month funding checkpoint have changed?
Trace the money that went out after a checkpoint. The Receipts Act could require independent progress approval before the next funding release.
Assumes review could prevent 100% of later spending. This includes payments for real work. Actual savings depend on which costs were avoidable, contract obligations, recoveries and assets kept.
Summit Texas Clean Energy reimbursements ↗
Approximately $116 million in DOE reimbursements through February 2016. This earlier cash snapshot is separate from the later $117.88 million funding figure.
- Cooperative agreement award month
- Jan 2010
- Funding checkpoint
- Apr 2010
- Cash spending definitely after it
- $0
- In a reporting period crossing it
- $116,000,000
1 cumulative reimbursement snapshot · exact payment dates remain missing
The source gives a cumulative amount inside a broad date window. A range starting at $0 means payment timing is unresolved. A $0 result after source coverage ends means later payments are uncollected.
Inspect the amounts, scope and source documents
Uses the report’s actual reimbursement total. The initial $15 million phase limit, $450 million commitment and $90 million funding shift do not establish dates of cash payments.
The month-only source produces a broad payment window. A three-month early checkpoint gives $0–$116 million before considering avoidability.
The report says funding was suspended in February 2016. Collected records end that month, so post-report payment totals remain unknown.
The later GAO funding amount cannot safely be subtracted from this rounded reimbursement snapshot without a common cash basis and closeout reconciliation.
Design work, financing commitments, cost-share disputes and recoveries still affect net savings.
| Record | Payment date or reporting window | Included amount |
|---|---|---|
| Summit Texas Clean Energy LLC | Jan 1, 2010 – Feb 29, 2016 | $116,000,000 |
The lower amount uses records entirely after the checkpoint, counting indistinguishable repeated rows once. The upper amount also includes periods crossing the checkpoint and unresolved repeated rows. Amounts are never spread evenly across unknown payment dates. Missing records remain outside the total. The selected review date may be later than the first warning.
Payment-record search · Dated expenditure snapshot added
Approximately $116 million in DOE reimbursements through February 2016. This earlier cash snapshot is separate from the later $117.88 million funding figure. Uses the report’s actual reimbursement total. The initial $15 million phase limit, $450 million commitment and $90 million funding shift do not establish dates of cash payments.
Still needed Obtain the reimbursement schedule, closeout payment ledger and actual repayments. A cumulative snapshot does not locate payments around the early checkpoint.
Reviewed November 9, 2026
Complete invoice-to-payment links
- Invoice
- What was charged.
- Payment record
- What was paid.
- Delivery record
- What was received.
Invoice + payment record
$0 linked hereNo matching invoice and payment records have been added to this file.
The circle shows the share of the displayed total with those records. Blue means linked here; gray means not linked here.
0% means no matching records are linked in this file. It does not describe every record the government holds or prove that money was lost or stolen.
Help make invoices, payments and proof of delivery public.
Support the Receipts ActHow this is measured and which records are linked
This file currently links summary-level sources, with no itemized invoice-to-payment records registered against this amount. The pie measures this collection only. Actual DOE project funding reported by GAO.
Only invoice and payment records tied to this same amount and scope count. Delivery coverage also requires a linked acceptance record. A report showing a total does not count as an individual receipt.
- Invoice, payment and delivery linked
- $0
- Invoice and payment linked; delivery not linked
- $0
- No matched invoice and payment in this file
- $117,876,707
0 matching invoice/payment records; 0 also link to delivery.
No individual invoice-to-payment records are registered in this file yet. This does not establish that those records do not exist elsewhere.
What is still missing?
Why was so much more early funding approved, and what accepted work did it produce?
Which records would help answer this?
The source establishes funding and failed construction delivery, but does not provide all paid claims and accepted design deliverables in a public reconciled ledger.
- Connect federal reimbursements and utility payments to invoices, work packages and accepted engineering milestones.
- Publish final termination costs, recovery amounts and the disposition or reuse of equipment and facilities.
- Separate taxpayer funding, ratepayer charges and private investment in a reconciled ledger.
These records have not all been assembled here. They may exist elsewhere. Personal details should stay protected.
Can we estimate how much was wasted or stolen?
This file does not establish an independent value for everything delivered. Subtracting a guessed value from a headline amount would not establish fraud. A sound estimate needs matching costs, delivered results and evidence about why any money was lost.
Sources and research notes (2 documents)
These documents support the case. A source document can describe many payments; it is not itself an itemized receipt.
- GAO-22-105111, table 3
gao.gov · 2021-12
- DOE OIG special report, reimbursements through February 2016
energy.gov · Reviewed 2026-11-09
Research cutoff: November 9, 2026. Older reports may not include later changes. Read our methodology.