The Department of Veterans Affairs is replacing its electronic health record system, but rollout has been limited and estimates have changed. The program continues.
Audit findings; delayed rollout
Ask Impact Analyst
Ask about the numbers or evidence. Keep the conversation going with follow-up questions.
By sending, you agree to share your question and this case’s notes with Google Gemini and save the conversation privately for review. Privacy
What was the money for?
Modernize veterans’ electronic health records.
The department’s April 2026 budget lists $10.5 billion in funding committed during 2018–2024. Its wording is “obligated actual spending”; this is not a payment-by-payment cash total or the full future cost.
Exact amount, time period and source wording
2018–2024 obligated actual spending as described in VA's FY2027 budget; not the total future program cost
Period: 2024
Putting the amount in context
average yearly funding committed in 2018–2024
The budget’s $10.5 billion over seven calendar years averages $1.5 billion a year.
What this comparison means: This averages committed funding, not cash paid each year or cost per patient. The total future program estimate has a broader scope.
How we calculated this and where it comes from
$10.5 billion ÷ 7 calendar years
Annual average of the source’s obligated amount, not cash paid in every year or cost per patient. The larger lifecycle forecast has a different scope.
What actually happened?
Some rollout and improvements occurred, but federal auditors called for updated costs and schedules. The April 2026 budget forecast about $37.2 billion overall, including the $10.5 billion already committed.
Keep in mind: The different forecasts cover different work and time periods. They must not be added together as separate losses.
Read the detailed findings
GAO found incremental improvements but a need for updated estimates and schedules. VA's April 2026 budget describes a roughly $37.2 billion forecast including $10.5 billion of 2018–2024 obligated actual spending.
Reported status: Continuing modernization with a limited rollout and revised cost forecasts; not a never-delivered system.
The earlier $16.1 billion and independent $49.8 billion estimates have different scopes. They are not additional amounts to add to the $37.2 billion forecast or $10.5 billion obligated figure.
Can we follow the payments?
A report can tell us the total. To follow the money, we also need to connect each bill to a payment and to what was received.
Payment records and reporting periods · reviewed November 9, 2026
What could a 3-month funding checkpoint have changed?
Trace the money that went out after a checkpoint. The Receipts Act could require independent progress approval before the next funding release.
Assumes review could prevent 100% of later spending. This includes payments for real work. Actual savings depend on which costs were avoidable, contract obligations, recoveries and assets kept.
VA electronic health record modernization ↗
Actual gross outlays for federal account 036-1123, FY2019–FY2025. Covers the account, including contract, infrastructure and program support.
- Cerner contract signed
- May 17, 2018
- Funding checkpoint
- Aug 17, 2018
- Cash spending definitely after it
- $9,445,000,000
7 annual actual-outlay records · individual payment dates remain unavailable
Inspect the amounts, scope and source documents
Only the actual column is imported. Estimated future years and obligations are excluded. Amounts are rounded to millions in the source. Gross outlays are before $55 million of reported offsets in FY2021, FY2024 and FY2025.
FY2018 and other accounts are outside this collection. This is not a payment-by-payment contract ledger.
The GAO date is a documented review checkpoint used here. Earlier concerns existed.
Stopping all account spending would also stop useful work and support. Patient safety, contractual liabilities, recoveries and retained systems require separate assessment.
| Record | Payment date or reporting window | Included amount |
|---|---|---|
| FY2019 | Oct 1, 2018 – Sep 30, 2019 | $512,000,000 |
| FY2020 | Oct 1, 2019 – Sep 30, 2020 | $991,000,000 |
| FY2021 | Oct 1, 2020 – Sep 30, 2021 | $1,342,000,000 |
| FY2022 | Oct 1, 2021 – Sep 30, 2022 | $1,670,000,000 |
| FY2023 | Oct 1, 2022 – Sep 30, 2023 | $2,229,000,000 |
| FY2024 | Oct 1, 2023 – Sep 30, 2024 | $1,285,000,000 |
| FY2025 | Oct 1, 2024 – Sep 30, 2025 | $1,416,000,000 |
- VA announces signed Cerner contract ↗
- GAO review of cost and schedule gaps ↗
- Budget Appendix, FY2019 actual gross outlays, account 036-1123 ↗
- Budget Appendix, FY2020 actual gross outlays, account 036-1123 ↗
- Budget Appendix, FY2021 actual gross outlays, account 036-1123 ↗
- Budget Appendix, FY2022 actual gross outlays, account 036-1123 ↗
- Budget Appendix, FY2023 actual gross outlays, account 036-1123 ↗
- Budget Appendix, FY2024 actual gross outlays, account 036-1123 ↗
- Budget Appendix, FY2025 actual gross outlays, account 036-1123 ↗
The lower amount uses records entirely after the checkpoint, counting indistinguishable repeated rows once. The upper amount also includes periods crossing the checkpoint and unresolved repeated rows. Amounts are never spread evenly across unknown payment dates. Missing records remain outside the total. The selected review date may be later than the first warning.
Payment-record search · Annual cash outlays added
Seven actual-year columns in federal budget appendices report $9.445 billion in gross outlays for account 036-1123 during FY2019–FY2025. Future estimates and obligations are excluded.
Still needed Collect FY2018 and later years, contract-level payment dates, account offsets and the value of usable systems. The account includes infrastructure and program support.
Reviewed November 9, 2026
The source describes money committed from 2018 to 2024. This is not a verified cash-payment total.
Complete invoice-to-payment links
- Invoice
- What was charged.
- Payment record
- What was paid.
- Delivery record
- What was received.
Invoice + payment record
$0 linked hereNo matching invoice and payment records have been added to this file.
The circle shows the share of the displayed total with those records. Blue means linked here; gray means not linked here.
0% means no matching records are linked in this file. It does not describe every record the government holds or prove that money was lost or stolen.
Help make invoices, payments and proof of delivery public.
Support the Receipts ActHow this is measured and which records are linked
This file currently links summary-level sources, with no itemized invoice-to-payment records registered against this amount. The pie measures this collection only. 2018–2024 obligated actual spending as described in VA's FY2027 budget; not the total future program cost.
Only invoice and payment records tied to this same amount and scope count. Delivery coverage also requires a linked acceptance record. A report showing a total does not count as an individual receipt.
- Invoice, payment and delivery linked
- $0
- Invoice and payment linked; delivery not linked
- $0
- No matched invoice and payment in this file
- $10,500,000,000
0 matching invoice/payment records; 0 also link to delivery.
No individual invoice-to-payment records are registered in this file yet. This does not establish that those records do not exist elsewhere.
What is still missing?
What did each payment deliver at each medical site, and did it improve safe, reliable care?
Which records would help answer this?
Forecast cost, obligations, invoice payments, adoption and patient-safety performance measure different things. This collection has no complete invoice-to-clinical-outcome reconciliation.
- Link each contract change and payment to tested software, accepted functionality and deployment milestones.
- Publish independent acceptance-test results, unresolved defects and service impacts, with sensitive details protected.
- Reconcile termination costs, recoveries and reused software or equipment.
These records have not all been assembled here. They may exist elsewhere. Personal details should stay protected.
Can we estimate how much was wasted or stolen?
This file does not establish an independent value for everything delivered. Subtracting a guessed value from a headline amount would not establish fraud. A sound estimate needs matching costs, delivered results and evidence about why any money was lost.
Sources and research notes (11 documents)
These documents support the case. A source document can describe many payments; it is not itself an itemized receipt.
- VA FY2027 budget, Volume 5
department.va.gov · 2026-04
- GAO-25-106874 EHR modernization
files.gao.gov · 2025
- VA announces signed Cerner contract
news.va.gov · Reviewed 2026-11-09
- GAO review of cost and schedule gaps
gao.gov · Reviewed 2026-11-09
- Budget Appendix, FY2019 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
- Budget Appendix, FY2020 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
- Budget Appendix, FY2021 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
- Budget Appendix, FY2022 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
- Budget Appendix, FY2023 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
- Budget Appendix, FY2024 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
- Budget Appendix, FY2025 actual gross outlays, account 036-1123
govinfo.gov · Reviewed 2026-11-09
Research cutoff: November 9, 2026. Older reports may not include later changes. Read our methodology.